The newest information about the exam belongs in your inbox, not on a forum. GetValidTest builds it into the product: daily monitoring, automatic email alerts, and materials that evolve as the PK0-003 exam does.
CompTIA PK0-003 Exam Overview:
| Certification Vendor: | CompTIA |
|---|---|
| Exam Name: | CompTIA Project+ |
| Exam Number: | PK0-003 |
| Real Exam Qty: | 100 |
| Exam Price: | USD 285 |
| Available Languages: | English |
| Related Certifications: | CompTIA Project+ |
| Passing Score: | 710 (on a scale of 100-900) |
| Exam Duration: | 90 minutes |
| Certificate Validity Period: | Good for Life (GFL) |
| Exam Format: | Multiple choice |
| Sample Questions: | ![]() |
| Exam Way: | Delivered through Pearson VUE authorized testing centers. |
| Pre Condition: | No prerequisite exam required. Recommended experience includes approximately one year of managing or participating in small to medium-sized projects. |
| Official Syllabus URL: | https://www.comptia.org/certifications/project |
CompTIA PK0-003 Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Project Planning | - Scope, schedule, and budget planning
|
| Project Closure | - Closing activities
|
| Project Basics | - Project characteristics and constraints
|
| Project Execution | - Team and communication management
|
| Project Control | - Monitoring and change management
|
PK0-003 Exam FAQ — Career, Convenience, Current News
GetValidTest issues a full refund if you take the CompTIA Project+ exam within 60 days of purchase and do not pass. The policy does not apply if the exam is taken within 3 days of purchase, if the exam was never actually taken, or to free materials or expired orders, and the candidate name must match the payer name. Submit a scan of your enrollment slip and the official Score Report PDF within 2 days of the exam; claims are processed within 7 days. Alternatively, exchange for two free exam products of equal value and keep your original update service. Orders arrive by email within 1 minute — contact support if nothing arrives within 2 hours.
The CompTIA Project+ exam contains 100 to complete within 90 minutes. Timed simulation in the GetValidTest Desktop Test Engine teaches that rhythm before exam day does.
Delivered through Pearson VUE authorized testing centers. Register for the CompTIA Project+ exam through these official channels:
After booking, GetValidTest delivers your practice questions within 1 minute — preparation starts the same day.
The CompTIA Project+ exam requires 710 (on a scale of 100-900) to pass, and registration costs USD 285. A failed attempt means paying the same fee again — a readiness check with the GetValidTest engines before booking is the cheaper option.
The PK0-003 exam is a CompTIA certification exam validating the CompTIA Project+ syllabus shown above. It belongs to these credential paths: CompTIA Project+. Candidates in 2026 start with GetValidTest's 320 practice questions, available as a printable PDF, a Windows Desktop Test Engine, and an Online Test Engine — three versions of the same materials.
No prerequisite exam required. Recommended experience includes approximately one year of managing or participating in small to medium-sized projects. Since requirements change over time, confirm the latest on the official CompTIA exam page before scheduling.
The official CompTIA Project+ outline defines 5 domains. The leading three are Project Control, Project Planning, and Project Closure. The full list is in the topics section above, and GetValidTest's 320 practice questions cover each one.
CompTIA recommends these training resources for the CompTIA Project+ exam:
Follow the training with steady self-testing — the 320 practice questions from GetValidTest help you apply theory and fill any gaps the training leaves.
Three versions of the same study materials: a printable, expert-prepared PDF with free demo download and instant access; a Desktop Test Engine for Windows with customizable simulation and timed modes that works offline; and an Online Test Engine for any browser on Windows, Mac, Android, and iOS with test history and performance review. All 320 practice questions are identical across versions. Every purchase includes 365 days of free updates, a 50% renewal discount afterward, and unlimited computer installations.
CompTIA Project+ Sample Questions:
The project manager has been informed the project's CPI is 0.85 on a multi-year project that is 30% complete. Which of the following actions would be BEST for the project manager to take?
- A. Ask the project sponsor to extend the project schedule.
- B. Fast track the project to reduce risk.
- C. Submit an RFQ to find a less expensive material.
- D. Assign additional team members to Quality Control.
Correct Answer: C 🗳️
Which of the following types of closure occurs when a project has been delivered to the satisfaction of all parties?
- A. Project cancellation
- B. Project completion
- C. Project post mortem
- D. Project phase closure
Correct Answer: B 🗳️
A project stakeholder wants to make changes to a project after work on the project has already started. Which of the following should the project manager do FIRST?
- A. Assign the request a tracking number and record in change request log
- B. Submit stakeholder's change request to the change control board
- C. Perform an analysis on the requested change submitted by the stakeholder
- D. Recruit new project team members to expedite the change's completion date
Correct Answer: A 🗳️
The project manager is trying to determine what to present at a project kick-off meeting. Should a high-level project schedule be included?
- A. Yes. High level project schedules are typically presented at a kick-off meeting.
- B. No. The project is likely to still be in the initiation phase which is too early for a project schedule.
- C. It depends. Some stakeholders are not technical enough to understand them.
- D. Yes. Project schedules are required to ensure that stakeholders are bound to the scope.
Correct Answer: A 🗳️
A project manager has been asked by a major stakeholder to modify the scope of a project in progress. Which of the following is the best FIRST step?
- A. Call a meeting and ensure all stakeholders agree to the changes.
- B. Submit a change request to the PMO.
- C. Assess the impact the change will have on the project.
- D. Obtain written approval from the project sponsor and make the requested changes.
Correct Answer: C 🗳️