NCARB Project-Management Exam Overview:
| Certification Vendor: | NCARB |
|---|---|
| Exam Name: | ARE 5.0 Project Management (PjM) |
| Exam Number: | PjM |
| Exam Price: | $235 USD |
| Passing Score: | Scaled score determined by NCARB |
| Real Exam Qty: | 75 |
| Available Languages: | English |
| Certificate Validity Period: | No rolling clock expiration policy |
| Exam Duration: | 180 minutes |
| Exam Format: | Case Study, Hotspot, Check-all-that-apply, Drag-and-place, Multiple Choice |
| Related Certifications: | Architect Licensure Architect Registration Examination (ARE 5.0) |
| Sample Questions: | ![]() |
| Exam Way: | Computer-based exam delivered at PSI test centers and online proctored locations |
| Pre Condition: | Candidates must obtain ARE eligibility through a U.S. jurisdiction and typically complete or be actively completing the Architectural Experience Program (AXP). |
| Official Syllabus URL: | https://www.ncarb.org/pass-the-are/prepare/project-management |
NCARB Project-Management Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Contracts | 25% | - Owner-Architect Agreements
|
| Project Execution | 30% | - Project Delivery
|
| Resource Management | 15% | - Financial Management
|
| Project Work Planning | 30% | - Scheduling and Work Planning
|
Before You Book the Project-Management Exam: Read These
Currently, the Project-Management exam's passing score is Scaled score determined by NCARB and the registration fee is $235 USD. Both are NCARB's figures and subject to revision — verify them on the official site before you schedule.
Reliability here is built, not claimed. The Project-Management bank is written by a team of IT experts and certified trainers with a wealth of knowledge in the NCARB ARE 5.0 Project Management (PjM) field, and we constantly keep it updated. The online test engine is the signature service: it fits the atmosphere of the actual test in advance, supports Windows, Mac, Android, and iOS, carries no installation limits, and lets you practice anytime, anywhere — perfectly suited to IT workers. Download the free sample first to learn about the product, and know that after purchase you may request the latest version at any time on top of 365 days of automatic updates.
The NCARB ARE 5.0 Project Management (PjM) blueprint covers these core domains:
- Project Work Planning (30%)
- Resource Management (15%)
- Contracts (25%)
Further domains complete the official outline; the bank addresses every one.
Upon successful payment, our system automatically sends the product to your mailbox — typically within about a minute — with an instant download link on screen. If nothing arrives within two hours, check your spam folder and contact our 24/7 online support. Updates are free for 365 days: whenever a new version is released, we send the updated bank to your mailbox automatically — and you can also request the latest version from us at any time. A 50% renewal discount applies when the period ends.
NCARB states the following prerequisites for the NCARB ARE 5.0 Project Management (PjM): Candidates must obtain ARE eligibility through a U.S. jurisdiction and typically complete or be actively completing the Architectural Experience Program (AXP)..
Confirm the details on the official certification page before registering.
According to the latest exam information, the Project-Management exam includes 75 questions and allows 180 minutes minutes. The online engine reproduces those conditions so practice matches the formal test's atmosphere.
Clear and dependable. If you fail the corresponding exam within 60 days of purchase, send the score report to our support team together with a scanned copy of your enrollment slip — the official Score Report PDF must reach us within two days of the exam date — and verified claims receive a full refund within seven days. Exclusions: exams taken within three days of purchase, candidate names that differ from the payer, and free or expired products. If you have another test in mind, you may instead wait for the next update or exchange your product for two others of equal value at no cost.
NCARB ARE 5.0 Project Management (PjM) Sample Questions:
An architect is evaluating a change order.
Where should the costs for the project superintendent or general foreman be included?
- A. Direct field labor costs
- B. General and administrative overheads
- C. Field overheads
- D. Direct field labor hours
Correct Answer: C 🗳️
Explanation: Only visible for GetValidTest members. You can sign-up / login (it's free).
What is the primary purpose of a punch list?
- A. To list all contract documents
- B. To identify incomplete or deficient work before final payment
- C. To summarize project milestones
- D. To schedule subcontractors
Correct Answer: B 🗳️
Explanation: Only visible for GetValidTest members. You can sign-up / login (it's free).

Refer to the exhibit
Twenty-five acres of undeveloped rural property was purchased for the site of a new elementary school.
During the DD phase, the civil engineer and structural engineers make design proposals based on the information provided in the geotechnical report. The civil engineer indicates that several cubic yards of fill material should be installed within the proposed building footprint to make up for the change in topography (was uniformly). The structural engineer indicates a footing depth of 24 inches for the entire facility. During the CD phase, the owner asks the architect to add classrooms to one wing. The civil engineer proposes that extra fill should not be installed beneath the additional classrooms.
Which of the following should the architect do before completion of CDs? Check the three that apply.
- A. Request an updated geotechnical evaluation
- B. Schedule a quality assurance meeting with the project team
- C. Increase the footing depth beneath the new classrooms
- D. Add general notes about structural bearing to the drawings
- E. Notify the structural engineer of the civil engineer's recommendation
- F. Update the estimate of the cost of work
Correct Answer: A,E,F 🗳️
Explanation: Only visible for GetValidTest members. You can sign-up / login (it's free).
Which four factors will most affect the choice of project delivery method? Check the four that apply.
- A. Construction cost
- B. Size of architectural firm
- C. Building code
- D. Project scope
- E. Owner risk tolerance
- F. Owner capabilities
Correct Answer: A,D,E,F 🗳️
Explanation: Only visible for GetValidTest members. You can sign-up / login (it's free).
Which of the following best describes "value engineering"?
- A. Reviewing project design and construction for cost-saving alternatives without compromising function
- B. Eliminating structural components to reduce cost
- C. Reducing the project schedule by adding labor
- D. Increasing the project scope to add value
Correct Answer: A 🗳️
Explanation: Only visible for GetValidTest members. You can sign-up / login (it's free).